Energy
Second Greece–Italy power link (GRITA 2) moves forward
IPTO and TERNA plan 1 GW of additional transmission capacity. Seabed surveys follow in early 2027, tenders for submarine cables and converter stations at the end of 2027, awards in 2028, operation from 2033.
Source: energypress.eu · dated