Giga Storage plans 1.4 GWh "Albatross" battery storage in Lower Saxony
The 350 MW / 1,400 MWh storage facility is to be connected directly to Amprion's 380 kV grid at the Merzen substation; final investment decision planned for Q4 2026, construction start in H1 2027, commissioning in 2028.