Energy
Giga Storage secures financing and grid connection for 350 MW "Albatross" storage project in Lower Saxony
The battery storage project near Neuenkirchen (350 MW / 1.4 GWh) receives €260 million in debt from seven banks and will connect directly to the 380 kV Merzen substation under an agreement with Amprion; construction starts in early 2027, commissioning in early 2029.
Source: pv magazine Deutschland · dated